The system
What sits against what, from the substrate outwards. Junctions, movement joints and edge details are project-specific — send us the drawings and we will mark them up.
Priming and sealing sequence
The moisture reading, not the calendar, decides when the sealer goes on.
Performance data
Taken from the manufacturers' own technical data sheets, with the standard each figure was measured against. Product-level figures are on the product pages below.
| Property | Result | Standard |
|---|---|---|
| Primer 100 — consumption | 6 – 8 m²/L per coat, undiluted | Cemher data sheet |
| Primer 100 — touch dry | 30 minutes; overcoat window 30 minutes to 8 hours | Cemher data sheet |
| Primer 100 — VOC | Declared VOC content nil in the manufacturer's data sheet — ask us for the content certificate before specifying against a VOC limit | Cemher data sheet |
| Primer 100 — application range | 0 °C to 30 °C; density 1.04 g/cm³ | Cemher data sheet |
| Maxipur 100% — consumption | 8 – 9 m²/L | Cemher data sheet |
| Maxipur 100% — drying | Touch dry 4 hours at 23 °C; fully dry 24 hours; recoat 4 hours to 3 days | Cemher data sheet |
| Maxipur 100% — type | Two-component aliphatic acrylic polyurethane, gloss, satin or matt | Cemher data sheet |
| Maxipur 100% — conditions | 12 – 25 °C, relative humidity below 80% | Cemher data sheet |
| AURO No. 301 — consumption | Approx. 0.05 L/m² per coat; dilute 1:1 with water for priming | AURO data sheet |
| AURO No. 301 — drying | Re-coatable after 4 to 6 hours; fully dry after 48 hours | AURO data sheet |
| AURO No. 301 — VOC | Product VOC < 1 g/L against an EU limit of 30 g/L (2004/42/EC II A (a)(Wb)) | AURO data sheet |
| AURO No. 301 — permeability | Open-pored, DC value < 0.1 m | AURO data sheet |
Products in this family
One page per technical data sheet. Each carries the manufacturer's declared figures, the limits, a specification clause and the full document set.
Where not to use it
Specifying a material into the wrong place is the most expensive mistake on a finishes package. These are the limits we will raise at review whether or not they are asked about.
- Maxipur is solvent-based. Specify Aquamax where a water-based sealer is required.
- Sealing before the finish is below 5% moisture traps water in the build-up.
- Primer 100 must be used undiluted.
- AURO No. 301 is for mineral interior substrates under clay finishes, not a general-purpose primer.
- Shelf life 24 months for all three, stored cool, dry and frost-free.
Primers and sealers: Cemher Primer 100 adhesion promoter applied undiluted at 6–8 m²/L, first finish coat applied not less than 30 minutes and not more than 8 hours afterwards. Finish sealed with Cemher [Maxipur 100% two-component polyurethane in matt / satin / gloss] at 8–9 m²/L, applied not less than 24 hours after the finish has hardened and only when substrate moisture is below 5% measured by meter. Recoat interval 4 hours, maximum 3 days.
Square brackets mark the choices that belong to the project. Send us the finishes schedule and we will return the clause completed, with the sample and mock-up programme against it.
Document library
Every publishable document for this family, reproduced in full and unaltered under our cover. Free to download, no form.
-
Auro Plaster Primer No 301 Primers and sealers · Technical data sheet · 3 pp · 0.9 MBDownload (PDF, 0.9 MB)
-
Maxipur 100 Primers and sealers · Technical data sheet · 11 pp · 0.8 MBDownload (PDF, 0.8 MB)
-
Primer 100 Primers and sealers · Technical data sheet · 8 pp · 0.7 MBDownload (PDF, 0.7 MB)
-
MAXIPUR 100% Primers and sealers · Voc emissions certificate · issued by Pinturas Kilnher, S.L., Valencia, Spain · 2 pp · 0.6 MBDownload (PDF, 0.6 MB)
-
MAXIPUR 100% Primers and sealers · Safety data sheet · 21 pp · 0.9 MBDownload (PDF, 0.9 MB)
-
MAXIPUR 100% Primers and sealers · Safety data sheet · 21 pp · 1 MBDownload (PDF, 1.0 MB)
Featured projects
Built with this material, by our own artisans. Open the project for the full set of photographs and the story of the installation.
Related systems
Technical support for the design team
We supply the material and we apply it, so the specification and the workmanship sit with one party. Send a finishes schedule, an elevation or a mood board and we will come back with the system, the build-up, the sample programme and a completed clause.